WHAT A 1GW AI DATA CENTER COSTS: ABOUT $30B, AND $17B OF IT IS CHIPS
Summary from the TLDR Hardware newsletter
An Abilene-scale build requires roughly $17B for chips and servers, $3B for power, and only $2.4B for construction. Transformers, generators, and cooling equipment face long lead times and rising prices.